MPS BUILDING COMMITTEE MEETING

Oliphant Administration Building

Michael S. Pinto Conference Room

26 Oliphant Lane, Middletown, RI 02842

July 15, 2026, 4:30pm

Members in Attendance:

Present

Voting

Member

Name

Title

X

Yes

Edward Brady

Chair, Community Member

X

Yes

William Nash

Vice Chair, School Committee Clerk

X

Yes

William Niemeyer

Superintendent of Schools

X

Yes

Tami Holden

School Committee Member

X

Yes

Ed Collins

Middletown Shared Facilities Director

N

Yes

Thomas P. Welch, III

Town Council Vice President

X*

Yes

Peter Connerton

Town Council Member

R

Yes

Donna Sweet

Middletown High School Principal

X

Yes

Michelle Fonseca

Asst Superintendent for Teaching and Learning

R

Yes

Shawn Brown

Town Administrator, Local Budget Official

X

Yes

Don Morin

Secretary, Community Member

X

Yes

Marc Thayer

Community Member

X

Yes

Dan Thibeault

Community Member

N

Alternate

Gregory Huet

Alternate Member of School Committee

N

Alternate

Christopher Logan

Alternate Town Council Member

X

Alternate

Jerry Haas

Gaudet Middle School Principal

X

Alternate

Marc Tanguay

Town Finance Director, Alt. Local Budget Official

 

 

X = Present/Voting; R=Represented; P=Present/Non-voting; N=Not Present

* Peter Connerton arrived at 4:32pm

1. Call to Order

1. The meeting was called to order at 4:30 pm by Ed Brady. Eleven (11) of thirteen (13) voting  members were present or represented by an alternate.

2. Also present: Justin Bernard, Colliers Project Leaders

3. Present via Zoom: Colin McCarthy, Colliers Project Leaders; Matt LaRue, Tina Stanislaski,  HMFH Architects; Ed Cifune and Emma Osborne, DBVW Architects

2. Consider and Vote on Meeting Minutes from June 10, 2026

MOTION: Don Morin moved to accept the meeting minutes from June 10, 2026, and Marc  Thayer seconded.

DISCUSSION: None 

VOTE: The motion passed unanimously (11-0).

3. Architect’s Update

3.1 No Update

1

4. Owners Rep Update:

4.1 Revised MOA (Memorandum of Agreement) Review

Justin Bernard informed the Building Committee that on June 25, 2026, RIDE (Ri Dept. of  Education) approved an amendment to the MOA to move the funding for Aquidneck  Elementary School renovations to the Forest Avenue Elementary School.

This brings the current eligible reimbursement numbers to the following:

Original MOA: $207,141,672

$170,486,682 new Middle School/High School

$26,879,690 Valley Elementary School

$4,288,845 Forest Ave Elementary School

$5,486,455 Aquidneck Elementary School

Revised MOA: $207,141,672

$170,486,682 new Middle School/High School

$26,879,690 Valley Elementary School

$9,775,000 Forest Ave Elementary School

$0 Aquidneck Elementary School

4.2 Forest Avenue Schematic Design RIDE Stage III Package Review

Justin reminded the Committee that the original estimated budget of $6,244,825  was based on the 2021 facility condition assessment.

The new proposed budget based on schematic design drawings with subcontractor  estimates is $7,460,000.

Included in the schematic design are ADA (Americans with Disabilities) upgrades, a  new elevator, new HVAC (Heating, Ventilation, Air Conditioning) systems, new 

windows, new flooring in the 1993 wing, a new sprinkler system, new playgrounds  and remodeled bathrooms.

The updated budget falls within the available funding.

Colliers requests the approval of the SBC to submit the Stage III Schematic Design  Package to RIDE following the July 16th SD review meeting with the RIDE School  Building Authority.

4.2.1 Consider and Vote to Approve Colliers to submit the Forest Avenue Schematic  Design RIDE Stage III Package to the RIDE SBA (School Building Authority) Portal MOTION: Don Morin moved that the Building Committee authorize Colliers to  submit the Forest Avenue Schematic Design RIDE Stage III package to the RIDE

School Building Authority portal.

DISCUSSION: None

VOTE: The motion passed unanimously (12-0).

4.3 MSHS Project Update

Justin Bernard shared information from Gilbane’s monthly dashboard report. Safety Update

2

Justin shared that the project remains at two recordable injuries and one lost  time injury, which is no change from last month.

Document Control

The number of submittals and RFIs in review has decreased significantly  from last month. The design team is doing a great job of getting them

closed out in a timely fashion.

69 Submittals in review

5 RFI’s (Requests for Information) in review

Schedule

Some upcoming milestones include interior gypsum wallboard, interior room  mockups, and exterior window delivery.

Gilbane will be mocking some interior rooms to show what the finished product  will look like.

The delivery of the exterior windows is very early for a project like this, which is  unusual but good for the project. The subcontractor is storing the windows  until the masonry work is farther along so that the windows can be installed. Financial Status (as of June 30, 2026)

Estimated PCOs (Potential Change Orders): $1,048,106.

PCOs are being actively managed and chased down for final pricing. Just this  past week Gilbane change orders number four, five, six and seven were 

submitted and approved.

Financial management and change order management are gaining traction. Progress Photos

Drone Flyover – Justin shared the drone flyover from the second week of June and walked the group through some recent photos of construction progress. The project continues to move along at a good pace.

4.4 Valley Elementary Project Update

Justin provided the following update on the work at Valley Elementary: Safety

The project had one recordable injury that was heat related. One of the roofers  was suffering from some heat-related illness and was hospitalized. He is back at  work but did miss all of Friday due to his heat injury.

Document Control

0 Submittals in review

0 RFIs in review

The project team is doing an excellent job keeping up with these.

Schedule

Upcoming milestones include the abatement completion at the roof, door &  frame mock-ups, plumbing rough ins at the bathrooms and nurse’s suite, and  elevator shoring and foundations.

Financial Status (as of July 10, 2026)

Estimated PCO’s: $235,820

Progress Photos

3

Justin shared some progress photos with the Committee.

4.5 Master Schedule Update

Justin shared that the only schedule change is for the building envelope completion  date at the middle high school. This seems to be moving in and out as Gilbane  further refines its overall schedule. 

There have been no changes to the major milestones.

4.6 Budget Update

Justin shared the following budget update, stating that biggest change is the increase in  available funding to over $203 million with the addition of the welding shop grants and  an increase in bond interest.

Project Funding Available: $203,166,162

$190,000,000 Bond Funded

$484,308 Appropriation from General Fund

$5,665,000 Bond Interest (as of July 2, 2026)

$5,700,000 Bond Premium 

$249,751 NEVI Grant

$1,067,103 Welding Shop Grants

Project Budget: $201,274,100

o Middle/High School: $173,623,000

o Valley Elementary: 20,182,100

o Forest Avenue Elementary: $7,469,000

o Justin added that the welding work hasn’t been added to the project budget  yet, so the project cost will increase by a little over a million dollars.

Expenditures to Date: $54,278,300

Contracted: $170,965,800

Total Anticipated Costs (excluding Contingences): $190,984,200

4.7 Four Week Look Ahead 

The MS/HS project will continue with exterior utilities & drainage, concrete slabs,  Air Vapor Barrier, exterior masonry, roofing, spray fireproofing, interior & exterior  framing & sheathing, and MEP fire protection rough-in.

The Valley Elementary project will continue with roof abatement; roofing; gym, café  & hallway painting; framing, MEP fire protection rough in; stair lifts; and elevator  shaft shoring & excavation.

The Forest Avenue Elementary School RIDE Schematic Design submission and Design  Development phase will continue.

The update from Colliers can be viewed here:

https://drive.google.com/file/d/1zBIRLtANmPH32g9mzDrO1i2OsOFsXTvG/view?usp =sharing.

4

5. School Building Committee Update

5.1 MSHS Welding Shop CTE (Career & Technical Education) Program Update

Superintendent Niemeyer informed the Building Committee that funding for the  welding CTE program has been received from the van Beuren Charitable Foundation.

5.2 Cultural, Historical, Memorial Subcommittee Update

Bill Nash stated that the committee has not met since the last Building Committee  meeting but that a presentation regarding the plans that the subcommittee have been  working on will be shared at the next meeting.

5.3 Four Week Look Ahead

Ed Collins stated that furniture for the middle school/high school is ready to go. A  meeting to discuss equipment is planned for Friday. FF&E for Valley Elementary will go  out to bid later this summer.

The next Building Committee meeting will be on August 12th at 4:30pm.

Adjournment: 

MOTION: Peter Connerton moved for the Building Committee to adjourn at 5:16pm and  Marc Thayer seconded. The motion passed unanimously (12-0).

Respectfully Submitted,

Don Morin

 

 

 